Amazon funds 12 nuclear reactors at retired Indiana coal site

Amazon will fund development of a proposed 960-megawatt nuclear plant of 12 Xe-100 reactors at a retired Indiana coal site, announced on 19 October 2026, and buy its power under a long-term contract.

4 min read
Amazon funds 12 nuclear reactors at retired Indiana coal sitePhoto: TechCrunch

Key points

Amazon, X-energy and AEP agreed to evaluate a 960-megawatt plant of 12 Xe-100 reactors at Indiana's retired Breed Generating Station, announced on 19 October 2026.

Amazon, X-energy and American Electric Power signed agreements on 19 October 2026 to evaluate a proposed 960-megawatt nuclear plant at the retired Breed Generating Station in Sullivan County, Indiana. The plant would use 12 Xe-100 small modular reactors, each rated at 80 megawatts, configured in three groups of four. Amazon would fund development and intends to buy the power under a long-term contract.

The project matters because it would connect advanced reactors to the public electric grid rather than a single industrial customer, while Amazon says the power would also serve its data centers. It is the second project under Amazon and X-energy's collaboration to add more than 5 gigawatts of new U.S. nuclear capacity by 2039, three times larger than their first deal, announced two years earlier.

What the agreement covers

AEP described the arrangement as a joint development agreement with X-energy, with Amazon supporting the project through a funding agreement. AEP chairman, president and chief executive Bill Fehrman said the agreements "will provide all necessary capital protections and financial safeguards that we have said are essential for any potential nuclear project to move forward." The plant would proceed only if the development reaches a final investment decision.

Amazon's vice president of data center infrastructure capacity delivery, Josh Weissman, said the companies aim to develop nearly a gigawatt of carbon-free power for the regional grid and pay their full costs without passing them to others. Amazon expects the plant to serve both the grid and its data centers, and linked the project to its participation in the White House Ratepayer Protection Pledge.

The Xe-100 is an 80-megawatt high-temperature gas-cooled reactor that uses helium as its coolant and tri-structural isotropic (TRISO) particle fuel — uranium particles encapsulated in ceramic layers engineered to retain fission products at high temperatures. Amazon states the reactor's physics prevent a meltdown without active systems or human intervention. The plants can use air-cooled, water-cooled or hybrid systems, which Amazon says suits water-constrained regions.

How the reactor works

The site is the former Breed Generating Station, a coal-fired plant south of Terre Haute that has been demolished. Amazon states the facility could create more than 1,000 construction jobs and more than 100 permanent jobs. If built, AEP says it would supply the regional grid and could operate for more than 60 years. Sullivan County recently joined the Indiana Advanced Nuclear Ready Communities Program.

Indiana Governor Mike Braun said the companies' decision to explore the technology represents innovation and investment that can deliver lasting benefits for the state, pointing to potential jobs in Sullivan County. Indiana Michigan Power, the AEP utility whose former Breed station would host the project, says the agreements are designed to provide financial safeguards for AEP's customers and investors.

The timeline depends on X-energy delivering its first plant at Dow's Seadrift complex on the Texas Gulf Coast, where it has yet to break ground. The site has been the subject of a lawsuit filed by the state of Texas, which accuses the plant of "habitual non-compliance" with water and solid-waste regulations. X-energy says its construction permit is in the final phases of Nuclear Regulatory Commission review.

What must happen next

X-energy debuted on the Nasdaq in April in an initial public offering priced at $23 per share; the price rose 27% on the first day but shares have since dropped by nearly two-thirds. News of the Amazon deal sent shares up about 10% in pre-market trading, though they were down by less than 2% at publication. X-energy says the Indiana proposal is its third announced U.S. Xe-100 project.

Amazon led X-energy's Series C-1 financing round in 2024 through its $2 billion Climate Pledge Fund; the round closed at $700 million, funding reactor design and licensing work and the first phase of X-energy's TRISO-X fuel fabrication facility in Oak Ridge, Tennessee. The companies' collaboration targets more than 5 gigawatts of new U.S. nuclear capacity by 2039.

Frequently asked questions

What did Amazon announce for Indiana?

Amazon, X-energy and American Electric Power signed agreements on 19 October 2026 to evaluate a proposed 960-megawatt nuclear plant at the retired Breed Generating Station in Sullivan County, Indiana, using 12 Xe-100 reactors. Amazon would fund development and buy the power under a long-term contract.

How large is the proposed Indiana nuclear plant?

The plant would use 12 Xe-100 small modular reactors of 80 megawatts each, configured in three groups of four reactors totalling 320 megawatts, for a combined 960 megawatts serving the regional grid and Amazon's data centers.

When will the Indiana nuclear plant be built?

No construction or operation timeline has been announced. The project requires a final investment decision, Nuclear Regulatory Commission licensing, interconnection approvals through PJM, and financing decisions, all described as multi-year processes.